DOCUMENTATION IN BOILER COMMISSIONING

 BOILER AND AUX. COMMISSIONING

It is the end of the erection process and the beginning of the operation. It consists of 14 days of nonstop operation and 72 hours of full-load operation.



INTRODUCTION TO COMMISSIONING

Before taking over a plant, commissioning activities are performed.

•Purpose –To ensure that the plant is delivered in accordance with the design –Quality of erection and commissioning –Plant operates reliably, safely, and according to the design –Determining the cause of any failure to meet the design performance.

Organization

advertisement

–Policies and priorities are set by the steering committee. Assures that sufficient resources are available. Documents must be approved. – G.M. is in charge.

–Commissioning panel – Oversight and tracking of day-to-day operations. Collaboration between the test teams and the working groups. Working groups in the Erection and O&M department look after the needs of the Test team.

–Testing and Commissioning Team – Responsible for testing and commissioning.

DOCUMENTATION IN BOILER COMMISSIONING

advertisement

1.Principal papers 

– Prepared jointly by Erection and corporate O.S. •To establish principles and objectives

•Established design data for plant comparison.

•Specify the documentation needed.

Testing and commissioning

2. Commissioning and testing 

•Meet the requirements of the principle paper

 •Plant undercover 

•Detail test method and programme 

•Safety 

•Emergencies 

•Individual responsibility 

•Results

advertisement

3. Checklist of essentials

•Ensuring erection completion •Limited-area operation •Conductance testing in a consistent manner •Instrument providing a schedule with range and resolution, as well as calibration validation

4.Notification of design changes

5. Reports on the tests

Recording of the outcome Analysis of the omission report

6. Procedure for ensuring safety

advertisement

7. Plant certification.

Certificate of safety clearance

Initial operation's record

Certificate of station operation clearance

Certificate of initial takeover

Internal contract clearance – guarantee period completion

Report on the plant's completion. – Acceptance and evaluation of PG tests